Amtrak Says Madison's Time Has Come for Passenger Rail — and This Time the Money Is Real
With a $218 million federal grant in hand and a friendly governor on the way, the railroad's development chief calls Dane County ‘a slam-dunk kind of market.’ The Hiawatha West extension would put two trains a day into downtown Madison.

Amtrak's top development executive says the railroad is in its “best position ever” to restore passenger trains to Madison, pointing to a $218 million federal grant awarded in October and a newly friendly state government — more than fifty years after the city's last regular service ended.
Arun Rao, Amtrak's senior director of state partnerships and development, told the Wisconsin State Journal that Dane County is “a slam-dunk kind of market for intercity passenger rail,” citing rapid population growth, UW–Madison, the state Capitol and the region's technology and biotech sectors. “This is the best position we've been in to get this done, ever,” he said.
The immediate cause for optimism is money. In October the Federal Railroad Administration announced a grant of more than $218 million to the Wisconsin Department of Transportation for final design and construction of the proposed Hiawatha West route, which would extend the existing Chicago–Milwaukee Hiawatha to Pewaukee, Watertown and Madison. The grant requires the state to cover 20 percent of the project cost, up to roughly $54.5 million.
This is the best position we've been in to get this done, ever.
The route would bring trains into downtown Madison along the John Nolen Drive corridor, extending two trains a day of what Rao called an already very successful intercity service. Madison's 2027 capital budget, adopted last week, includes $3.5 million for passenger rail, and the DOT is requesting $52 million for the project in the 2027–29 state budget. The total extension is estimated at $272.5 million.
Politics, long the project's graveyard, has shifted. A high-speed rail line to Madison died in 2011 when Gov. Scott Walker rejected $810 million in federal stimulus money — a decision he defended last year. This month Democrats took control of state government for the first time in 16 years, and Gov.-elect David Crowley has said he would accept the grant, calling the extension “exactly the kind of investment that moves people, creates jobs, and builds a stronger state.”
Crowley's defeated opponent, Republican U.S. Rep. Tom Tiffany, had opposed using state tax dollars to build the line or to pay a $2.5 million annual operating subsidy. Rao declined to comment on the election's effect on funding, saying only that Amtrak has consistently seen “tremendous, broad support” from communities along the route — including a willing host in the Wisconsin & Southern Railroad.
A downtown station is taking shape along Wilson Street. The city picked the corridor as its preferred location last November, and in June the state approved selling the State Office Building at 1 W. Wilson St. to a developer that plans to convert its lower floors into an Amtrak station. A city-owned parking lot at 499 E. Wilson St. could serve as a temporary station, said Liz Callin, Madison's principal transportation planner.
What remains is sequence. Amtrak expects approval of the route's service development plan by early next year, then preliminary engineering and environmental review, then final design and construction. After half a century of false starts, the pieces — money, host railroad, station site, state politics — have for once landed on the same side of the board.